Not just a line crew.
Solar developers and EPCs need a contractor who understands the utility interconnection process, medium-voltage construction standards, and the field engineering judgment to solve problems that arise between design and construction.
McDonough Electric brings all of it. Our northern NH operations are positioned directly in the active ISO-NE interconnection queue for solar and storage projects in New Hampshire and Maine.
Gilford, NH Solar Interconnect
The original engineering specification called for a horizontal switch configuration. When equipment was delivered, it arrived as a vertical switch — a deviation that would have caused schedule-killing delays for most contractors.
Ryan McDonough developed a field engineering solution on-site: reroute the switch to a dedicated riser pole, relocate the recloser to an adjacent pole, and reconfigure the framing to accommodate the vertical equipment — all within Eversource NH interconnect specifications.
Eversource approved the solution. Zero schedule impact.
- Interconnect switch installation
- Recloser and protection equipment
- Overhead conductor and framing
- Riser pole construction
- Cutout and arrester installation
- Field engineering support
- GOAB switch installation
- Recloser installation
- Overhead conductor
- Framing and hardware
- Utility-grade specifications
- Testing coordination
- Underground MV cable
- Overhead MV collection
- Combiner and collection points
- Pad-mount equipment
- Underground duct bank
- Utility interconnection
- Eversource NH experience
- CMP service territory
- ISO-NE queue knowledge
- Spec deviation resolution
- Utility approval management
- Construction to commissioning
- SCADA communications fiber
- Control building fiber
- Splice and termination
- Fiber to substation
- Integrated MV and fiber scope
- Single contractor delivery
- On-site spec problem solving
- Utility-compliant solutions
- Equipment substitution management
- No schedule impact approach
- Coordination with EPC
- Documentation for utility approval
in the ISO-NE queue?





